Vinh Loc 2 Industrial Zone

Long An Province

Project Overview

Property type

Industrial Park

Location

Ben Luc District, Long An Province

Industrial Park

Vinh Loc 2 Industrial Park

Developer

Vinh Loc- Ben Luc Industrial Zone Construction And Investment Corporation

Target Industries

Clothing, Machinery, Consumer Goods...

Major Tenant Companies

Viet Trung, SLP, MPE

Scale

561.5 ha

Industrial Land

225.98 ha

Land Use Term

2061

Regional Minimum Wage

Zone II

Tax Incentives

Tax exemption for the first 2 years

Technical Specifications

Supply Voltage

22 kV

Water Supply

5,000 m³ / day

Wastewater Treatment

10,000 m³ / day

Location

Distance to Airports:

  • Tan Son Nhat International Airport (SGN): 28 km
  • Can Tho International Airport (VCA): 141 km
  • Long Thanh International Airport (LTH): 63 km

Distance to Ports:

  • Hiep Phuoc Port: 28 km
  • Long An International Port: 31 km
  • Cat Lai Port: 37 km

Distance to City Centres & Routes:

  • Ho Chi Minh City: About 28 km via National Highway 1
  • Can Tho City: About 131 km via National Highway 1

Key Highlights

Vinh Loc 2 Industrial Park is a multi-sector industrial park in Voi La Hamlet, My Yen Commune, Tay Ninh Province (formerly Long Hiep Commune, Ben Luc District, Long An Province). It sits at KM 1929-1930 on National Highway 1A, next to Binh Chanh District (Ho Chi Minh City).

The park has operated since 2011, with a land use period running to 2061. The original master plan covered 561.5 ha, and the 2026 adjusted subdivision plan sets the scale at 223.2 ha. It is about 25 km from central Ho Chi Minh City and about 4 km from Bourbon Port (Ben Luc).

This article gives you the information to evaluate the park: scale, infrastructure, location, industries and incentives. It ends with an assessment of whether leasing land here makes sense. Please confirm the details with the developer, or contact RSQUARE for more information, before making a decision.

Overview of Vinh Loc 2 Industrial Park

Vinh Loc 2 Industrial Park has Vinh Loc – Ben Luc Industrial Park Investment & Construction Joint Stock Company as its infrastructure developer. The company was established on 22/04/2008 and previously developed Vinh Loc 1 Industrial Park in Binh Tan District, Ho Chi Minh City.

Item Details
Industrial Park Name Vinh Loc 2 Industrial Park
Address KM 1929-1930, National Highway 1A, Voi La Hamlet, My Yen Commune, Tay Ninh Province (formerly: Long Hiep Commune, Ben Luc District, Long An Province)
Infrastructure Developer Vinh Loc – Ben Luc Industrial Park Investment & Construction JSC
Operating Since 2011
Land Use Period Until 2061

Industrial Park Scale

Vinh Loc 2 Industrial Park had an original master plan of 561.5 ha, but its current scale under the 2026 adjusted subdivision plan is 223.2 ha. The 561.5 ha figure is the planned area across two phases. It is not the area of the park currently in operation.

Parameter Value
Original total master plan 561.5 ha
Phase 1 (in operation) 259.8 ha, including 225.98 ha of industrial land and 33.6 ha of residential land
Phase 2 (under the old plan) 301.7 ha, status: under development
Scale after adjustment (2026) 223.2 ha
– Industrial production and warehouse land 152.2 ha
– Transport land 37.2 ha
– Green space 23.6 ha
– Administrative and service land 7.89 ha
– Technical infrastructure land 2.29 ha
Building density 68.2% under the adjusted plan (the developer previously stated 70%); factories up to 5 stories, warehouses up to 4 stories
Occupancy rate Over 90%, according to a reference source updated in 05/2026
Minimum rental area From 1 ha, according to some brokerage sources

The 223.2 ha scale is stated per Decision 141/QĐ-BQLKKT dated 13/04/2026 of the Tay Ninh Provincial Economic Zone Management Board, according to a reference source. Building density and minimum rental area depend on the detailed plan for each plot and on the developer’s conditions, so you should confirm them before preparing your plan.

Infrastructure

The park’s infrastructure includes internal roads connecting to National Highway 1A, a 40 MVA / 22 kV power supply from a 110/22 kV substation, water from the Go Den water supply station, and a centralized wastewater treatment plant meeting QCVN 24:2009/BTNMT Column A.

Summary of the park’s technical specifications:

Item Specification
Wastewater treatment 8,000 m³/day
Water supply 12,000 m³/day (maximum capacity)
Electricity supply 40 MVA / 22 kV

Transportation system

Internal roads connect directly to National Highway 1A. According to the developer’s description, the main roads have a right-of-way of 30-47 m and an asphalt concrete surface, and each plot borders at least two roads. The 2026 adjusted plan allocates 37.2 ha to transport land. Specific road standards should be confirmed against the developer’s design documents.

Distances from the park to major trade points (estimated by road; they vary with the reference point and route):

Destination Distance
Ho Chi Minh City center Approx. 25 km
Tan Son Nhat Airport Approx. 28 km
Saigon Port Approx. 27 km
Bourbon Port (Ben Luc) Approx. 4 km
Saigon Railway Station Approx. 26.6 km
Phu My Hung Urban Area Approx. 22 km
An Lac Intersection Approx. 14 km
Nguyen Van Linh Intersection Approx. 10 km

Electricity supply

The park receives power from the national grid through a 110/22 kV substation. The developer states that Phase 1 draws power from the Go Den 110/22 kV substation. According to a reference source, the 2026 adjusted plan documents state the supply comes from the Ben Luc 110/22 kV substation via the 22 kV grid of Vinh Loc Electricity JSC.

The summary specifications give the park’s power supply as 40 MVA at 22 kV. There is no data yet on the supply scope for each phase or on the remaining capacity. For projects with large power demand, you should ask the developer or EVN to confirm.

Water supply

Clean water comes from the Go Den water supply station through a pipeline along National Highway 1A. Phase 1 water supply capacity is 5,000-7,000 m³/day. According to the plan, Phase 2 raises capacity to 7,000-12,000 m³/day, which matches the maximum capacity of 12,000 m³/day in the summary specifications. You should confirm the actual schedule and capacity with the developer.

Wastewater treatment

The park’s centralized Wastewater Treatment Facility has a design capacity of 8,000 m³/day, and the treated water meets QCVN 24:2009/BTNMT Column A. Wastewater from factories is collected through D300 and D400 sewer lines to the centralized treatment station.

Design capacity differs from operating capacity and from remaining available capacity. Before signing a land lease contract, you need to confirm three things with the developer and the Management Board: the current operating capacity, the influent wastewater parameters accepted, and the project’s connection feasibility.

On-site utilities and services

Vinh Loc 2 Industrial Park and its surrounding area have utilities that support businesses, workers and production safety. According to reference information, these include:

  • Telecommunications: telecom network and fiber-optic internet. The actual carrier and bandwidth should be confirmed for each plot.
  • Fire protection: fire hydrants are placed along internal roads at a maximum spacing of 150 m, per general technical requirements. Fire protection and acceptance documents should be checked with the developer.
  • Services and amenities: the adjusted plan allocates 7.89 ha to administrative and service land. There is also worker accommodation, plus banking, healthcare and education services in the nearby Ben Luc area.

Soil conditions and load-bearing capacity vary by plot location, soil layer and groundwater level. Businesses should commission a separate geological survey for each plot before designing a factory, especially for heavy-load structures.

Location and Regional Connectivity

Vinh Loc 2 Industrial Park lies at the western gateway of Ho Chi Minh City, right on National Highway 1A and bordering Binh Chanh District. Key location advantages:

  • About 25 km from central Ho Chi Minh City, convenient for distributing goods to the Ho Chi Minh City market and neighboring areas.
  • About 4 km from Bourbon Port (Ben Luc) and about 27 km from Saigon Port, suitable for import-export businesses.
  • About 28 km from Tan Son Nhat Airport and 26.6 km from Saigon Railway Station.

Allowed Industries

Vinh Loc 2 Industrial Park attracts multi-sector investment, prioritizing projects that meet environmental regulations and the park’s treatment capacity. The main industry groups, according to reference sources:

  • Agro-, forestry-, aquatic and seafood processing and food: food, animal feed, beverages, soft drinks.
  • Chemicals, plastics and pharmaceuticals: fertilizers, plastics, plastic packaging, pharmaceuticals, medicinal herbs, chemicals and cosmetics.
  • Mechanical engineering: precision engineering, machinery manufacturing, equipment, components and spare parts.
  • Electrical, electronics, telecommunications and IT: electrical equipment, electronic components, telecom equipment.
  • Textiles, garments, footwear, packaging and printing: apparel, footwear, packaging, printing.
  • Building materials and interior furnishings: construction materials, lightweight materials, interior decoration.

Excluded industries: the list excludes the production of monosodium glutamate (MSG), alcohol and pulp. This is a priority-industry list according to reference sources, not an absolute prohibition. Before signing a land lease contract, you need to check your project’s specific industry against the current industry list, the detailed plan and environmental regulations.

Key Tenants

The park hosts businesses in many fields, such as food, plastics, fertilizers, steel and textiles. The companies below are named by reference sources and have not been independently verified against the Management Board’s or developer’s list:

  • HURO Probiotics JSC (probiotics).
  • Saigon Plastic Color Co., Ltd. and Thanh Phu Plastic Packaging Co., Ltd. (plastics).
  • Israel Chemicals Fertilizer Group JSC and Agrium fertilizer company (fertilizers).
  • Nguyen Minh Steel Co., Ltd. and Nam Hung Steel Company (steel).
  • W&W Textile JSC (textiles) and Seowon Tech Vina Co., Ltd. (mechanical components and equipment).

Land Use Period and Legal Status

The Land Use Period of Vinh Loc 2 Industrial Park is recorded as running to 2061, giving an operating timeframe of 2011-2061. The exact end date should be checked against the current land allocation decision or land lease contract.

Planning milestones, according to reference sources:

  • 22/06/2017: Long An Provincial People’s Committee approved the 1/2,000 detailed plan (Decision 2313/QĐ-UBND).
  • 10/01/2022: Long An Provincial Economic Zone Management Board approved a partial adjustment of the 1/2,000 subdivision plan (Decision 08/QĐ-BQLKKT).
  • 13/04/2026: Tay Ninh Provincial Economic Zone Management Board approved the overall adjustment of the 1/2,000 subdivision plan (Decision 141/QĐ-BQLKKT).

Secondary enterprises pay land lease or sublease costs under their contract with the developer and fulfill tax, fee and charge obligations under current regulations. The fact that the developer has paid land rent to the State does not mean secondary enterprises are exempt from all land-related financial obligations.

Tax Incentives and Investment Policies

Enterprises carrying out eligible new investment projects may receive a corporate income tax exemption for the first 2 years and a 50% reduction in tax payable for the next 4 years. Incentives depend on the industry, location and conditions of each project under current tax law, and do not automatically apply to every enterprise leasing land. You need to confirm with the tax authority and the Economic Zone Management Board.

The developer may support enterprises in the following areas:

  • Advice on investment procedures and investment license documents at the Management Board.
  • Advice on design, construction, environmental impact assessment and fire protection plans.
  • Support with documents and procedures related to land use rights and ownership of structures; state agencies are the ones that issue the certificates.
  • Pricing policy and payment terms for each plot.

The scope, costs and conditions of support are the developer’s service commitments, not fixed legal regulations, so you should have them stated in writing or in the contract.

Should You Lease Land at Vinh Loc 2 Industrial Park?

Vinh Loc 2 Industrial Park suits businesses that need to produce close to Ho Chi Minh City, belong to approved industry groups, and accept limited remaining land. Assessment by need:

The park is a good fit if you:

  • Need a location right on National Highway 1A, about 25 km from central Ho Chi Minh City and about 4 km from Bourbon Port (Ben Luc), to reduce logistics costs.
  • Manufacture in food, plastics, mechanical engineering, electronics, textiles or building materials.
  • Want a long land use period, to 2061, and a park that has operated stably since 2011.

Consider carefully if:

  • Your project falls into the excluded industries, such as MSG, alcohol or pulp.
  • Your project generates a large volume of wastewater, because the operating treatment capacity and connection feasibility need to be confirmed.
  • Your project needs a large land bank, because the occupancy rate is recorded at over 90% and the scale after adjustment is down to 223.2 ha.
  • Your budget depends on the land lease price, because rates vary by time, plot and agreement with the developer.

Before deciding, you should ask the developer for a quotation, the layout of available plots, the building density of the plot, the current industry list, and confirmation of the available wastewater treatment capacity.

Investor Support Services at RSQUARE

RSQUARE offers a comprehensive consulting package for domestic and foreign investors at industrial parks nationwide, including:

  • Industrial real estate consulting
  • Site survey and plot visit services before contract signing
  • Support in introducing legal services for business licenses and investment registration certificates
  • Support in negotiating and signing land lease contracts
  • Support in connecting law firms and banks

With experience working directly with industrial park management boards and foreign investors, RSQUARE accompanies businesses from plot survey through completion of legal procedures and site handover.

Make an Inquiry

How can we help? Our team will get back to you soon.

1
Step 1
2
Step 2

Please enter the following information

Please enter the following information